How to use this calculator
- Enter gross exterior wall area.
- Subtract the estimated share occupied by openings.
- Set coats and observed crew productivity.
- Add prep labor, then choose crew size and workday length.
Estimate the hands-on time needed to paint a home exterior before scheduling a crew or comparing bids. The calculator adjusts wall area for doors and windows, multiplies it by the number of coats, and adds preparation time. Results show total labor-hours, expected crew-hours, and workdays so you can separate the amount of work from the calendar time.
Labor-hours measure the total worker effort. Crew-hours and workdays estimate elapsed time only when all crew members can work productively at the same time.
Weather, ladder moves, siding condition, and detailed trim can reduce real-world productivity. Use a conservative productivity rate when access is difficult.
For 2,400 sq ft of walls with 15% openings, two coats, 150 sq ft per labor-hour, and 16 prep hours: net area is 2,040 sq ft and total labor is 43.2 hours. A three-person crew needs about 14.4 crew-hours, or 1.8 eight-hour days.
Include primer when its application takes roughly the same effort as a finish coat; otherwise add its time to preparation labor.
The openings percentage removes unpainted area, but detailed masking may still require additional preparation hours.
Labor-hours add every worker's time, while crew-hours divide that effort across the crew to estimate elapsed time.
Use your crew's observed rate; textured or damaged siding generally requires a lower input than broad, smooth surfaces.
No. Drying and weather delays affect the schedule but are not active labor-hours.
| Variable | Meaning |
|---|---|
| Gross wall area | Exterior wall faces before deductions |
| Openings | Unpainted door and window share |
| Productivity | Square feet completed per labor-hour per coat |
| Prep labor | Separate cleaning, masking, and repair time |