How to use this calculator
- Enter the project quantity and operating assumptions.
- Use measured project rates where available.
- Select Calculate to update the result and supporting metrics.
- Change one input at a time to compare scenarios.
Calculate timber framing output per crew-hour and per worker-hour from completed wall area. This makes daily production and labor intensity visible while keeping crew size, shifts, and hours explicit.
Worker productivity = completed area ÷ (crew size × shift hours × shifts).
Crew-hour output describes the complete team’s pace. Worker-hour output normalizes for crew size and is useful when examining labor intensity.
Wall area alone does not capture roof, floor, stair, opening, hardware, or detailing complexity. Define the measured scope before comparing rates.
A six-person crew frames 4,800 sq ft in five 8-hour shifts. Crew output is 4,800 ÷ 40 = 120 sq ft per crew-hour; worker output is 20 sq ft per worker-hour.
Only if the measured area and historical comparison use the same combined scope; otherwise track them separately.
One crew-hour is one hour for the whole crew, while worker-hours multiply that time by crew size.
Not in this version; convert the completed wall scope to square feet for consistent results.
Normally no. Use accepted completed area so rework does not inflate output.
No. Congestion, supervision, material flow, and work-front limits can reduce efficiency as crew size grows.
| Variable | Unit | Use |
|---|---|---|
| Completed scope | sq ft | Accepted framed wall area |
| Crew time | hours × shifts | Elapsed team time |
| Labor-hours | workers × crew time | Total labor input |